• In Graduation Project II, we will apply theoretical concepts mentioned in Project one, which will be mainly the cost and time management.
• The main idea is to recalculate the cost and reschedule of Tulkarem Directorate of education building, which is already executed
Project Description
Project name Tulkarem Directorate of Education
Area of Land 750 m2
Total Area of building 1200 m2
Number of Stories 4
Project funded Ministry of Education
Project Consultant Engineering Dept. in DoE.
Date of Project 2004 to 2005
• Project start in 2/6/2012
• Working day = 8 hours
• Non-working days are Fridays and holydays
• Currency used US-Dollar, with exchange rate = 3.78 NIS
Electrical and Mechanical works have taken as lump sum
The main procedures in scheduling are:
o Substructure work.
o Super structure work.
o Finishing Work
Total Cost Percentages
Items Percentage (%)
Sub-Structure 8.61%
Super structure 43.75%
Finishing works 47.64%