Construction Project Management

Academic Year: 
2012
Students: 
Mohammed Jamal Tarif
Ahmed Usama Al-Ghool
Loay Ahmed Salahat
Department: 
Civil Engineering
Files: 
application/vnd.openxmlformats-officedocument.presentationml.presentation iconpresentation1.pptx

• In Graduation Project II, we will apply theoretical concepts mentioned in Project one, which will be mainly the cost and time management.

• The main idea is to recalculate the cost and reschedule of Tulkarem Directorate of education building, which is already executed  

Project Description

Project name Tulkarem Directorate of Education 

Area of Land 750 m2 

Total Area of building 1200 m2   

Number of Stories 4 

Project funded Ministry of Education 

Project Consultant Engineering Dept. in DoE. 

Date of Project 2004 to 2005 


• Project start in 2/6/2012

• Working day = 8 hours 

• Non-working days are Fridays and holydays

• Currency used US-Dollar, with exchange rate = 3.78 NIS

Electrical and Mechanical works have taken as lump sum




The main procedures in scheduling are: 

o Substructure  work.

o Super structure work.

o Finishing Work 



Total Cost Percentages

Items Percentage (%) 

Sub-Structure 8.61%

Super structure 43.75%

Finishing works 47.64%





 