Tulkarm municipality Building is a 2 floor building above the ground surface, the first one consists of stores and the second one contains the employees offices and meeting and Cafeteria and a Reception hall and a kitchen.
The building located in Tulkarm city in the western strip of the city.
The area of the first floor area is 1200.76 m2 same as the second floor .
The elevation of street is -1.1 and the elevation of the ground slab roof is 0.00 and the elevation of first slab roof is 5.45 and the elevation of the second slab roof is 9.0
At first we will plan the project normally and calculate the duration of the project and the total cost and the cost of resources.
The purpose of our study is to obtain the final cost, and duration for it. In order to obtain these values we followed the following steps:
Overview:
1-
Total project cost = 2489005 NIS.
2-
Profit & Overhead 20% from total cost.
3-
The cost of structural work is = 2267510 NIS.
The cost of mechanical work is = 64910 NIS .
The cost of electrical work is = 156585 NIS.