Home

Rehabilitation of Nablus Electrical Network by adding a new connection point

Academic Year: 
2016
Supervisors: 
Maher Khammash (Department Head)
Students: 
Ahmad Hatem Abd-Albaqi
Ali Namrouti
Department: 
Electrical Engineering
Files: 
application/vnd.openxmlformats-officedocument.presentationml.presentation iconpresentation_2.pptx

Abstract :

This  project aims to  study the performance of  Nablus Network and to add a new connection point in the eastern region of the city of Nablus in the village of " Huwwara " with maximum capacity up to 20 MW , in  cooperation with NEDCO ( Northern Electric Distribution Company)  .

Taking into consideration that  there are 6 connection points  in the electrical network of the  city of Nablus. 

 A load flow study and analysis for Nablus Electrical Networkusing ETAP software will be performed to see the effect of adding a new connection point to the network and to improve the power factor, improve the voltage level  and to reduce the electrical losses in the network , and so reducing the penalties in the total tariff  for the municipality, increasing the reliability of the network.

 To do that we will follow the sequence below:

 

1 .Collect correct data from NEDCO about Nablus electrical network.

2. Run it on software (ETAP) to get the results.

3. Study the network with the new connection point.

©2012 An-Najah National University|Faculty Of Engineering | P.O. Box: 7 | Nablus, Palestine | Phone: +970 (9) 2345113 Ext:2253 | Fax: +970 (9) 2345982 | email: [email protected]