Our project is to study and all points of interconnection Askar (23 MVA namely ) , Howwara (20 MVA namely ), Wadi Tuffah (23 MVA namely )and Central point (20 MVA namely ). Which means that we have chosen Wadi Tuffah in Nablus electrical network as a swing bus in order to unify the whole Nablus electrical network because we want to realize the minimum losses in the whole network .
In order to do that we’ll follow the sequence below :
Collecting data from NEDCO ( North Electricity Distribution Company ) about Nablus Network such as the one- line diagram , resistance , reactance , the nominal voltages , transformers primary and secondary voltages , loads , and many other requirements to analyze the network .
Drawing the one-line diagram using ETAP software and analyzing the network under different and analyzing the results .
Giving conclusion and recommendation .